Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in East Garfield Park

The typical renovation & alteration permit issued in East Garfield Park took 34 days. The 75th-percentile wait was 94 days.

Records checked4002021–Sep. 15, 2026

The short answer

Typical wait34 daysmedian issued permit
Usually within94 days75% of records
Long-wait edge183 days90% of records
Evidence400issued permits

The median was 39 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
19.2%
1–7 days
17.0%
8–30 days
12.5%
31–90 days
25.0%
91+ days
26.2%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021795 days49 days131 days
20229710 days62 days130 days
20236116 days82 days162 days
20246745 days142 days251 days
20256358 days87 days161 days
2026*3383 days170 days271 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
East Garfield Park34 days94 days400
Washington Park34 days118 days201
Woodlawn34 days98 days522
Albany Park33 days77 days422
Austin35 days97 days1,097
Englewood35 days97 days571
Lincoln Park33 days86 days1,340
Lincoln Square33 days82 days638