Renovation & Alteration permits in Woodlawn

The typical renovation & alteration permit issued in Woodlawn took 34 days. The 75th-percentile wait was 98 days.

Records checked5222021–Sep. 15, 2026

The short answer

Typical wait34 daysmedian issued permit
Usually within98 days75% of records
Long-wait edge188 days90% of records
Evidence522issued permits

The median was 0.5 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
15.5%
1–7 days
17.0%
8–30 days
15.3%
31–90 days
25.1%
91+ days
27.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211005 days64 days170 days
20221216 days70 days166 days
20238339 days119 days328 days
202410646 days96 days157 days
20256571 days105 days158 days
2026*4749 days102 days216 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
East Garfield Park34 days94 days400
Washington Park34 days118 days201
Woodlawn34 days98 days522
Albany Park33 days77 days422
Austin35 days97 days1,097
Englewood35 days97 days571
Lincoln Park33 days86 days1,340
Lincoln Square33 days82 days638