Community area × permit type
Renovation & Alteration permits in Lincoln Square
The typical renovation & alteration permit issued in Lincoln Square took 33 days. The 75th-percentile wait was 82 days.
Records checked6382021–Sep. 15, 2026
The short answer
Typical wait33 daysmedian issued permit
Usually within82 days75% of records
Long-wait edge162 days90% of records
Evidence638issued permits
The median was 2 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 117 | 3 days | 44 days | 101 days |
| 2022 | 121 | 2 days | 47 days | 118 days |
| 2023 | 106 | 34 days | 87 days | 137 days |
| 2024 | 104 | 42 days | 89 days | 182 days |
| 2025 | 96 | 59 days | 126 days | 200 days |
| 2026* | 94 | 59 days | 104 days | 201 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Albany Park | 33 days | 77 days | 422 |
| Lincoln Park | 33 days | 86 days | 1,340 |
| Lincoln Square | 33 days | 82 days | 638 |
| Mckinley Park | 33 days | 106 days | 176 |
| North Center | 33 days | 84 days | 755 |
| East Garfield Park | 34 days | 94 days | 400 |
| Greater Grand Crossing | 32 days | 95 days | 596 |
| Irving Park | 32 days | 85 days | 707 |