Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Lincoln Square

The typical renovation & alteration permit issued in Lincoln Square took 33 days. The 75th-percentile wait was 82 days.

Records checked6382021–Sep. 15, 2026

The short answer

Typical wait33 daysmedian issued permit
Usually within82 days75% of records
Long-wait edge162 days90% of records
Evidence638issued permits

The median was 2 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
18.7%
1–7 days
14.3%
8–30 days
15.4%
31–90 days
28.8%
91+ days
22.9%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211173 days44 days101 days
20221212 days47 days118 days
202310634 days87 days137 days
202410442 days89 days182 days
20259659 days126 days200 days
2026*9459 days104 days201 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Albany Park33 days77 days422
Lincoln Park33 days86 days1,340
Lincoln Square33 days82 days638
Mckinley Park33 days106 days176
North Center33 days84 days755
East Garfield Park34 days94 days400
Greater Grand Crossing32 days95 days596
Irving Park32 days85 days707