Renovation & Alteration permits in Mckinley Park
The typical renovation & alteration permit issued in Mckinley Park took 33 days. The 75th-percentile wait was 106 days.
Records checked1762021–Sep. 15, 2026
The short answer
Typical wait33 daysmedian issued permit
Usually within106 days75% of records
Long-wait edge202 days90% of records
Evidence176issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 38 | 0 days | 40 days | 210 days |
| 2022 | 45 | 1 day | 38 days | 137 days |
| 2023 | 24 | 32 days | 75 days | 131 days |
| 2024 | 30 | 48 days | 141 days | 207 days |
| 2025 | 26 | 105 days | 172 days | 284 days |
| 2026* | 13 | 72 days | 123 days | 197 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Albany Park | 33 days | 77 days | 422 |
| Lincoln Park | 33 days | 86 days | 1,340 |
| Lincoln Square | 33 days | 82 days | 638 |
| Mckinley Park | 33 days | 106 days | 176 |
| North Center | 33 days | 84 days | 755 |
| East Garfield Park | 34 days | 94 days | 400 |
| Greater Grand Crossing | 32 days | 95 days | 596 |
| Irving Park | 32 days | 85 days | 707 |