Renovation & Alteration permits in Englewood
The typical renovation & alteration permit issued in Englewood took 35 days. The 75th-percentile wait was 97 days.
Records checked5712021–Sep. 15, 2026
The short answer
Typical wait35 daysmedian issued permit
Usually within97 days75% of records
Long-wait edge182 days90% of records
Evidence571issued permits
The median was 46 days slower than the previous 12 months.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 106 | 6 days | 26 days | 84 days |
| 2022 | 111 | 5 days | 52 days | 132 days |
| 2023 | 99 | 46 days | 109 days | 226 days |
| 2024 | 107 | 54 days | 144 days | 240 days |
| 2025 | 82 | 46 days | 110 days | 171 days |
| 2026* | 66 | 98 days | 146 days | 244 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Austin | 35 days | 97 days | 1,097 |
| Englewood | 35 days | 97 days | 571 |
| Pullman | 35 days | 120 days | 99 |
| West Pullman | 35 days | 96 days | 192 |
| Beverly | 36 days | 91 days | 308 |
| Calumet Heights | 36 days | 86 days | 133 |
| East Garfield Park | 34 days | 94 days | 400 |
| Logan Square | 36 days | 100 days | 1,286 |