Renovation & Alteration permits in West Pullman
The typical renovation & alteration permit issued in West Pullman took 35 days. The 75th-percentile wait was 96 days.
Records checked1922021–Sep. 15, 2026
The short answer
Typical wait35 daysmedian issued permit
Usually within96 days75% of records
Long-wait edge163 days90% of records
Evidence192issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 36 | 15 days | 86 days | 135 days |
| 2022 | 51 | 0 days | 37 days | 111 days |
| 2023 | 30 | 10 days | 74 days | 134 days |
| 2024 | 23 | 73 days | 122 days | 167 days |
| 2025 | 31 | 57 days | 110 days | 202 days |
| 2026* | 21 | 96 days | 152 days | 373 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Austin | 35 days | 97 days | 1,097 |
| Englewood | 35 days | 97 days | 571 |
| Pullman | 35 days | 120 days | 99 |
| West Pullman | 35 days | 96 days | 192 |
| Beverly | 36 days | 91 days | 308 |
| Calumet Heights | 36 days | 86 days | 133 |
| East Garfield Park | 34 days | 94 days | 400 |
| Logan Square | 36 days | 100 days | 1,286 |