East Garfield Park permit processing times

For 1,600 issued permits in East Garfield Park, the median processing time was 3 days; 75% were issued within 28 days.

Records checked1,6002021–Sep. 15, 2026

The short answer

Typical wait3 daysmedian issued permit
Usually within28 days75% of records
Long-wait edge94 days90% of records
Evidence1,600issued permits

The median was 3 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
39.4%
1–7 days
23.1%
8–30 days
13.2%
31–90 days
13.7%
91+ days
10.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20212720 days10 days88 days
20223320 days7.2 days62 days
20232250 days7 days56 days
20242617 days38 days112 days
20253238 days42 days87 days
2026*18712 days62 days122 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Nearby points in the citywide timing distribution

ReportMedian75% withinRecords
East Garfield Park3 days28 days1,600
Grand Boulevard3 days34 days1,871
Lincoln Park3 days28 days6,764
North Park3 days18 days1,222
Uptown3 days21 days2,727
Woodlawn3 days27 days2,225
Douglas2.5 days21 days992
Avondale2 days21 days2,361