Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Signs permits in Beverly

The typical signs permit issued in Beverly took 11 days. The 75th-percentile wait was 27 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked722021–Sep. 15, 2026

The short answer

For Signs permits in Beverly, 72 issued permit records show a median processing time of 11 days; 75% were issued within 27 days and 90% within 110 days, covering January 2021 through September 15, 2026.

Typical wait11 daysmedian issued permit
Usually within27 days75% of records
Long-wait edge110 days90% of records
Evidence72issued permits

Not enough records for a year-over-year comparison.

Signs permits in Beverly: wait distribution

For Signs permits in Beverly, 72 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
5.6%
1–7 days
40.3%
8–30 days
30.6%
31–90 days
9.7%
91+ days
13.9%

Change over time

Signs permits in Beverly: annual permit timing

Signs permits in Beverly has 4 publishable issue-year cohorts spanning 2021–2024, representing 66 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
2021217 days28 days315 days
20221111 days76 days200 days
2023171 day3 days12 days
20241723 days27 days92 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in Beverly: Signs timing in comparable community areas

Signs permits in Beverly has 72 issued records, a 11 days median, and a 27 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Beverly11 days27 days72
Dunning10 days36 days72
Garfield Ridge10 days21 days242
Ohare10 days19 days111
Archer Heights13 days28 days115
Englewood13 days36 days77
Mckinley Park9 days22 days124
Norwood Park9 days26 days134