Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Near South Side

The typical new construction permit issued in Near South Side took 1 day. The 75th-percentile wait was 12 days.

Records checked2512021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within12 days75% of records
Long-wait edge47 days90% of records
Evidence251issued permits

The median was 2.5 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
37.1%
1–7 days
32.3%
8–30 days
16.3%
31–90 days
6.8%
91+ days
7.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021290 days0 days4 days
2022500 days0 days19 days
2023431 day34 days385 days
2024455 days16 days37 days
2025465 days12 days25 days
2026*389.5 days23 days55 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Hyde Park1 day5.2 days120
Loop1 day7 days554
Near South Side1 day12 days251
North Park2 days70 days39
Armour Square3 days70 days80
Oakland5 days114 days25
Near North Side7 days48 days350
South Shore7.5 days126 days30