Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in South Shore

The typical express permit program permit issued in South Shore took 1 day. The 75th-percentile wait was 9 days.

Records checked1,3202021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within9 days75% of records
Long-wait edge23 days90% of records
Evidence1,320issued permits

The median was 1 day faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
39.7%
1–7 days
33.0%
8–30 days
19.8%
31–90 days
5.7%
91+ days
1.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211390 days1 day8.4 days
20221580 days2 days23 days
20231510 days6 days19 days
20243273 days12 days22 days
20253264 days10 days25 days
2026*2194 days12 days27 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207