Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Signs permits in South Shore

The typical signs permit issued in South Shore took 24 days. The 75th-percentile wait was 77 days.

Records checked652021–Sep. 15, 2026

The short answer

Typical wait24 daysmedian issued permit
Usually within77 days75% of records
Long-wait edge179 days90% of records
Evidence65issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
1.5%
1–7 days
23.1%
8–30 days
32.3%
31–90 days
20.0%
91+ days
23.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021134 days58 days113 days
20242119 days179 days179 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs timing in comparable community areas

ReportMedian75% withinRecords
Logan Square24 days56 days408
South Shore24 days77 days65
Ashburn23 days71 days151
West Elsdon23 days97 days52
West Englewood25 days63 days43
West Pullman23 days36 days25
Albany Park22 days74 days140
Armour Square26 days47 days50