Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Signs permits in South Shore

The typical signs permit issued in South Shore took 24 days. The 75th-percentile wait was 77 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked652021–Sep. 15, 2026

The short answer

For Signs permits in South Shore, 65 issued permit records show a median processing time of 24 days; 75% were issued within 77 days and 90% within 179 days, covering January 2021 through September 15, 2026.

Typical wait24 daysmedian issued permit
Usually within77 days75% of records
Long-wait edge179 days90% of records
Evidence65issued permits

Not enough records for a year-over-year comparison.

Signs permits in South Shore: wait distribution

For Signs permits in South Shore, 65 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
1.5%
1–7 days
23.1%
8–30 days
32.3%
31–90 days
20.0%
91+ days
23.1%

Change over time

Signs permits in South Shore: annual permit timing

Signs permits in South Shore has 2 publishable issue-year cohorts spanning 2021–2024, representing 34 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
2021134 days58 days113 days
20242119 days179 days179 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in South Shore: Signs timing in comparable community areas

Signs permits in South Shore has 65 issued records, a 24 days median, and a 77 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Logan Square24 days56 days408
South Shore24 days77 days65
Ashburn23 days71 days151
West Elsdon23 days97 days52
West Englewood25 days63 days43
West Pullman23 days36 days25
Albany Park22 days74 days140
Armour Square26 days47 days50