Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Wrecking & Demolition permits in Near North Side

The typical wrecking & demolition permit issued in Near North Side took 50 days. The 75th-percentile wait was 93 days.

Records checked492021–Sep. 15, 2026

The short answer

Typical wait50 daysmedian issued permit
Usually within93 days75% of records
Long-wait edge159 days90% of records
Evidence49issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
44.9%
1–7 days
0.0%
8–30 days
0.0%
31–90 days
20.4%
91+ days
34.7%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2022120 days10 days88 days
2026*1592 days113 days149 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition timing in comparable community areas

ReportMedian75% withinRecords
Near North Side50 days93 days49
Albany Park0 days67 days28
Auburn Gresham0 days28 days44
Austin0 days50 days88
Avondale0 days38 days55
Bridgeport0 days50 days63
Chicago Lawn0 days0 days33
East Garfield Park0 days43 days33