Community area × permit type
Renovation & Alteration permits in Fuller Park
The typical renovation & alteration permit issued in Fuller Park took 20 days. The 75th-percentile wait was 98 days.
Records checked682021–Sep. 15, 2026
The short answer
Typical wait20 daysmedian issued permit
Usually within98 days75% of records
Long-wait edge219 days90% of records
Evidence68issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 13 | 1 day | 6 days | 411 days |
| 2022 | 10 | 0 days | 62 days | 85 days |
| 2023 | 10 | 25 days | 103 days | 164 days |
| 2024 | 16 | 22 days | 86 days | 219 days |
| 2025 | 10 | 48 days | 98 days | 117 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Fuller Park | 20 days | 98 days | 68 |
| Hyde Park | 20 days | 60 days | 448 |
| East Side | 21 days | 71 days | 96 |
| Oakland | 22 days | 131 days | 85 |
| Armour Square | 25 days | 76 days | 153 |
| Chatham | 26 days | 77 days | 444 |
| Near North Side | 13 days | 50 days | 2,586 |
| Auburn Gresham | 28 days | 96 days | 612 |