Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Portage Park

The typical renovation & alteration permit issued in Portage Park took 42 days. The 75th-percentile wait was 99 days.

Records checked5492021–Sep. 15, 2026

The short answer

Typical wait42 daysmedian issued permit
Usually within99 days75% of records
Long-wait edge161 days90% of records
Evidence549issued permits

The median was 14 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
18.0%
1–7 days
13.1%
8–30 days
12.0%
31–90 days
30.1%
91+ days
26.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021994 days58 days127 days
20221023.5 days97 days154 days
202310046 days119 days165 days
20249042 days91 days172 days
20259064 days99 days195 days
2026*6853 days88 days158 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Humboldt Park42 days104 days739
Jefferson Park42 days114 days251
Mount Greenwood42 days87 days153
Portage Park42 days99 days549
Roseland42 days104 days397
West Lawn42 days124 days138
Bridgeport41 days112 days410
Chicago Lawn43 days112 days356