Renovation & Alteration permits in Mount Greenwood
The typical renovation & alteration permit issued in Mount Greenwood took 42 days. The 75th-percentile wait was 87 days.
Records checked1532021–Sep. 15, 2026
The short answer
Typical wait42 daysmedian issued permit
Usually within87 days75% of records
Long-wait edge163 days90% of records
Evidence153issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 33 | 16 days | 55 days | 150 days |
| 2022 | 36 | 29 days | 43 days | 76 days |
| 2023 | 29 | 37 days | 70 days | 99 days |
| 2024 | 13 | 41 days | 68 days | 156 days |
| 2025 | 24 | 88 days | 109 days | 189 days |
| 2026* | 18 | 88 days | 155 days | 242 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Humboldt Park | 42 days | 104 days | 739 |
| Jefferson Park | 42 days | 114 days | 251 |
| Mount Greenwood | 42 days | 87 days | 153 |
| Portage Park | 42 days | 99 days | 549 |
| Roseland | 42 days | 104 days | 397 |
| West Lawn | 42 days | 124 days | 138 |
| Bridgeport | 41 days | 112 days | 410 |
| Chicago Lawn | 43 days | 112 days | 356 |