Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Mount Greenwood

The typical renovation & alteration permit issued in Mount Greenwood took 42 days. The 75th-percentile wait was 87 days.

Records checked1532021–Sep. 15, 2026

The short answer

Typical wait42 daysmedian issued permit
Usually within87 days75% of records
Long-wait edge163 days90% of records
Evidence153issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
15.7%
1–7 days
3.9%
8–30 days
18.3%
31–90 days
37.3%
91+ days
24.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20213316 days55 days150 days
20223629 days43 days76 days
20232937 days70 days99 days
20241341 days68 days156 days
20252488 days109 days189 days
2026*1888 days155 days242 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Humboldt Park42 days104 days739
Jefferson Park42 days114 days251
Mount Greenwood42 days87 days153
Portage Park42 days99 days549
Roseland42 days104 days397
West Lawn42 days124 days138
Bridgeport41 days112 days410
Chicago Lawn43 days112 days356