Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Official community area

Mount Greenwood permit processing times

For 898 issued permits in Mount Greenwood, the median processing time was 1 day; 75% were issued within 15 days.

Records checked8982021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within15 days75% of records
Long-wait edge62 days90% of records
Evidence898issued permits

The median was 3 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
49.1%
1–7 days
17.1%
8–30 days
15.6%
31–90 days
11.0%
91+ days
7.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211770 days9 days49 days
20221670 days12 days49 days
20231580 days11 days70 days
20241364 days19 days41 days
20251482 days22 days84 days
2026*1125.5 days36 days77 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Nearby points in the citywide timing distribution

ReportMedian75% withinRecords
Albany Park1 day14 days2,213
Archer Heights1 day14 days812
Ashburn1 day10 days2,411
Auburn Gresham1 day11 days3,290
Austin1 day14 days5,647
Belmont Cragin1 day13 days2,724
Beverly1 day13 days1,644
Burnside1 day9.5 days227