Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Mount Greenwood

The typical new construction permit issued in Mount Greenwood took 53 days. The 75th-percentile wait was 105 days.

Records checked292021–Sep. 15, 2026

The short answer

Typical wait53 daysmedian issued permit
Usually within105 days75% of records
Long-wait edge185 days90% of records
Evidence29issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
13.8%
1–7 days
3.4%
8–30 days
17.2%
31–90 days
34.5%
91+ days
31.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Bridgeport53 days151 days125
Mount Greenwood53 days105 days29
North Lawndale54 days145 days242
Avondale54 days98 days107
Irving Park52 days110 days185
Albany Park52 days123 days62
Dunning51 days150 days39
Edgewater51 days112 days91