Community area × permit type
New Construction permits in Irving Park
The typical new construction permit issued in Irving Park took 52 days. The 75th-percentile wait was 110 days.
Records checked1852021–Sep. 15, 2026
The short answer
Typical wait52 daysmedian issued permit
Usually within110 days75% of records
Long-wait edge185 days90% of records
Evidence185issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 49 | 13 days | 89 days | 148 days |
| 2022 | 28 | 14 days | 116 days | 200 days |
| 2023 | 30 | 40 days | 80 days | 179 days |
| 2024 | 27 | 77 days | 117 days | 252 days |
| 2025 | 28 | 71 days | 132 days | 201 days |
| 2026* | 23 | 69 days | 96 days | 126 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Irving Park | 52 days | 110 days | 185 |
| Albany Park | 52 days | 123 days | 62 |
| Bridgeport | 53 days | 151 days | 125 |
| Dunning | 51 days | 150 days | 39 |
| Edgewater | 51 days | 112 days | 91 |
| Mount Greenwood | 53 days | 105 days | 29 |
| North Lawndale | 54 days | 145 days | 242 |
| Avondale | 54 days | 98 days | 107 |