Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Bridgeport

The typical new construction permit issued in Bridgeport took 53 days. The 75th-percentile wait was 151 days.

Records checked1252021–Sep. 15, 2026

The short answer

Typical wait53 daysmedian issued permit
Usually within151 days75% of records
Long-wait edge500 days90% of records
Evidence125issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
18.4%
1–7 days
0.8%
8–30 days
14.4%
31–90 days
28.8%
91+ days
37.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20214220 days44 days175 days
20221928 days54 days179 days
202314144 days418 days597 days
20241171 days129 days490 days
202527132 days440 days679 days
2026*1256 days136 days177 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Bridgeport53 days151 days125
Mount Greenwood53 days105 days29
North Lawndale54 days145 days242
Avondale54 days98 days107
Irving Park52 days110 days185
Albany Park52 days123 days62
Dunning51 days150 days39
Edgewater51 days112 days91