Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in North Lawndale

The typical new construction permit issued in North Lawndale took 54 days. The 75th-percentile wait was 145 days.

Records checked2422021–Sep. 15, 2026

The short answer

Typical wait54 daysmedian issued permit
Usually within145 days75% of records
Long-wait edge209 days90% of records
Evidence242issued permits

The median was 88 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
24.0%
1–7 days
13.6%
8–30 days
5.4%
31–90 days
24.0%
91+ days
33.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021220 days0 days56 days
2022410 days0 days161 days
2023317 days129 days253 days
20242448 days75 days165 days
202580144 days154 days221 days
2026*4452 days81 days135 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
North Lawndale54 days145 days242
Avondale54 days98 days107
Bridgeport53 days151 days125
Mount Greenwood53 days105 days29
Humboldt Park55 days112 days227
Irving Park52 days110 days185
Albany Park52 days123 days62
Dunning51 days150 days39