North Lawndale permit processing times

For 2,708 issued permits in North Lawndale, the median processing time was 2 days; 75% were issued within 29 days.

Records checked2,7082021–Sep. 15, 2026

The short answer

Typical wait2 daysmedian issued permit
Usually within29 days75% of records
Long-wait edge111 days90% of records
Evidence2,708issued permits

The median was 3 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
43.0%
1–7 days
19.1%
8–30 days
13.4%
31–90 days
12.7%
91+ days
11.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20214930 days9 days77 days
20225140 days3 days68 days
20234500 days14 days106 days
20244587 days42 days102 days
20254879 days65 days151 days
2026*30613 days53 days127 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Nearby points in the citywide timing distribution

ReportMedian75% withinRecords
Avondale2 days21 days2,361
Bridgeport2 days24 days1,920
Brighton Park2 days19 days1,507
Englewood2 days24 days2,131
Lake View2 days23 days6,844
Logan Square2 days29 days5,067
Loop2 days15 days15,467
Lower West Side2 days31 days2,358