Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in North Lawndale

The typical renovation & alteration permit issued in North Lawndale took 41 days. The 75th-percentile wait was 105 days.

Records checked6542021–Sep. 15, 2026

The short answer

Typical wait41 daysmedian issued permit
Usually within105 days75% of records
Long-wait edge198 days90% of records
Evidence654issued permits

The median was 26 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
18.0%
1–7 days
13.0%
8–30 days
13.3%
31–90 days
26.6%
91+ days
29.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211476 days68 days119 days
20221214 days75 days156 days
202310030 days105 days196 days
202412956 days113 days201 days
20259974 days140 days229 days
2026*5892 days178 days261 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Bridgeport41 days112 days410
Gage Park41 days95 days173
North Lawndale41 days105 days654
Humboldt Park42 days104 days739
Jefferson Park42 days114 days251
Mount Greenwood42 days87 days153
Portage Park42 days99 days549
Roseland42 days104 days397