Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Renovation & Alteration permits in Bridgeport

The typical renovation & alteration permit issued in Bridgeport took 41 days. The 75th-percentile wait was 112 days.

Records checked4102021–Sep. 15, 2026

The short answer

Typical wait41 daysmedian issued permit
Usually within112 days75% of records
Long-wait edge196 days90% of records
Evidence410issued permits

The median was 8 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
18.0%
1–7 days
10.2%
8–30 days
15.9%
31–90 days
23.9%
91+ days
32.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021841 day60 days163 days
20228312 days98 days197 days
20236839 days113 days234 days
20248056 days132 days198 days
20256173 days109 days202 days
2026*3468 days149 days190 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Renovation & Alteration timing in comparable community areas

ReportMedian75% withinRecords
Bridgeport41 days112 days410
Gage Park41 days95 days173
North Lawndale41 days105 days654
Humboldt Park42 days104 days739
Jefferson Park42 days114 days251
Mount Greenwood42 days87 days153
Portage Park42 days99 days549
Roseland42 days104 days397