Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Wrecking & Demolition permits in North Lawndale

The typical wrecking & demolition permit issued in North Lawndale took 0 days. The 75th-percentile wait was 55 days.

Records checked882021–Sep. 15, 2026

The short answer

Typical wait0 daysmedian issued permit
Usually within55 days75% of records
Long-wait edge151 days90% of records
Evidence88issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
62.5%
1–7 days
0.0%
8–30 days
1.1%
31–90 days
21.6%
91+ days
14.8%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20211746 days189 days205 days
2022130 days77 days184 days
2024270 days55 days55 days
2025120 days0 days0 days
2026*1046 days76 days91 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Wrecking & Demolition timing in comparable community areas

ReportMedian75% withinRecords
Albany Park0 days67 days28
Auburn Gresham0 days28 days44
Austin0 days50 days88
Avondale0 days38 days55
Bridgeport0 days50 days63
Chicago Lawn0 days0 days33
East Garfield Park0 days43 days33
Edgewater0 days49 days49