Community area × permit type
New Construction permits in Humboldt Park
The typical new construction permit issued in Humboldt Park took 55 days. The 75th-percentile wait was 112 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in Humboldt Park, 227 issued permit records show a median processing time of 55 days; 75% were issued within 112 days and 90% within 201 days, covering January 2021 through September 15, 2026.
The median was 16 days slower than the previous 12 months.
New Construction permits in Humboldt Park: wait distribution
For New Construction permits in Humboldt Park, 227 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in Humboldt Park: annual permit timing
New Construction permits in Humboldt Park has 6 publishable issue-year cohorts spanning 2021–2026, representing 227 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 43 | 6 days | 57 days | 97 days |
| 2022 | 42 | 0.5 days | 54 days | 205 days |
| 2023 | 25 | 83 days | 143 days | 196 days |
| 2024 | 23 | 43 days | 116 days | 150 days |
| 2025 | 56 | 73 days | 113 days | 197 days |
| 2026* | 38 | 76 days | 137 days | 322 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in Humboldt Park: New Construction timing in comparable community areas
New Construction permits in Humboldt Park has 227 issued records, a 55 days median, and a 112 days 75th-percentile wait in this release.
| Report | Median | 75% within | Records |
|---|---|---|---|
| Humboldt Park | 55 days | 112 days | 227 |
| Avondale | 54 days | 98 days | 107 |
| North Lawndale | 54 days | 145 days | 242 |
| Bridgeport | 53 days | 151 days | 125 |
| Garfield Ridge | 57 days | 182 days | 39 |
| Grand Boulevard | 57 days | 96 days | 245 |
| Mount Greenwood | 53 days | 105 days | 29 |
| Irving Park | 52 days | 110 days | 185 |
More New Construction permits in Humboldt Park comparisons
The New Construction permits in Humboldt Park cohort contains 227 issued records; related links retain separate location and permit-category cohorts.