Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Avondale

The typical new construction permit issued in Avondale took 54 days. The 75th-percentile wait was 98 days.

Records checked1072021–Sep. 15, 2026

The short answer

Typical wait54 daysmedian issued permit
Usually within98 days75% of records
Long-wait edge266 days90% of records
Evidence107issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
22.4%
1–7 days
6.5%
8–30 days
8.4%
31–90 days
35.5%
91+ days
27.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021220 days56 days90 days
20222216 days69 days98 days
20231875 days128 days303 days
20242248 days188 days406 days
20251298 days247 days297 days
2026*1164 days69 days122 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Avondale54 days98 days107
North Lawndale54 days145 days242
Bridgeport53 days151 days125
Humboldt Park55 days112 days227
Mount Greenwood53 days105 days29
Irving Park52 days110 days185
Albany Park52 days123 days62
Dunning51 days150 days39