Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Dunning

The typical new construction permit issued in Dunning took 51 days. The 75th-percentile wait was 150 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked392021–Sep. 15, 2026

The short answer

For New Construction permits in Dunning, 39 issued permit records show a median processing time of 51 days; 75% were issued within 150 days and 90% within 197 days, covering January 2021 through September 15, 2026.

Typical wait51 daysmedian issued permit
Usually within150 days75% of records
Long-wait edge197 days90% of records
Evidence39issued permits

Not enough records for a year-over-year comparison.

New Construction permits in Dunning: wait distribution

For New Construction permits in Dunning, 39 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
20.5%
1–7 days
10.3%
8–30 days
7.7%
31–90 days
25.6%
91+ days
35.9%

Change over time

New Construction permits in Dunning: annual permit timing

New Construction permits in Dunning has 2 publishable issue-year cohorts spanning 2022–2025, representing 21 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20221024 days151 days230 days
20251196 days158 days186 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction permits in Dunning: New Construction timing in comparable community areas

New Construction permits in Dunning has 39 issued records, a 51 days median, and a 150 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Dunning51 days150 days39
Edgewater51 days112 days91
Albany Park52 days123 days62
Irving Park52 days110 days185
Norwood Park50 days104 days62
Mckinley Park50 days148 days50
Bridgeport53 days151 days125
Mount Greenwood53 days105 days29