New Construction permits in Norwood Park
The typical new construction permit issued in Norwood Park took 50 days. The 75th-percentile wait was 104 days.
Records checked622021–Sep. 15, 2026
The short answer
Typical wait50 daysmedian issued permit
Usually within104 days75% of records
Long-wait edge154 days90% of records
Evidence62issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2022 | 17 | 45 days | 73 days | 136 days |
| 2023 | 10 | 44 days | 105 days | 205 days |
| 2026* | 10 | 60 days | 121 days | 170 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Norwood Park | 50 days | 104 days | 62 |
| Mckinley Park | 50 days | 148 days | 50 |
| Dunning | 51 days | 150 days | 39 |
| Edgewater | 51 days | 112 days | 91 |
| Albany Park | 52 days | 123 days | 62 |
| Belmont Cragin | 48 days | 110 days | 42 |
| Forest Glen | 48 days | 139 days | 34 |
| Irving Park | 52 days | 110 days | 185 |