Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Belmont Cragin

The typical new construction permit issued in Belmont Cragin took 48 days. The 75th-percentile wait was 110 days.

Records checked422021–Sep. 15, 2026

The short answer

Typical wait48 daysmedian issued permit
Usually within110 days75% of records
Long-wait edge199 days90% of records
Evidence42issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
14.3%
1–7 days
19.0%
8–30 days
7.1%
31–90 days
31.0%
91+ days
28.6%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20231342 days113 days140 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Belmont Cragin48 days110 days42
Forest Glen48 days139 days34
Washington Park48 days102 days108
Mckinley Park50 days148 days50
Jefferson Park46 days71 days78
Norwood Park50 days104 days62
Dunning51 days150 days39
Edgewater51 days112 days91