New Construction permits in Forest Glen

The typical new construction permit issued in Forest Glen took 48 days. The 75th-percentile wait was 139 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked342021–Sep. 15, 2026

The short answer

For New Construction permits in Forest Glen, 34 issued permit records show a median processing time of 48 days; 75% were issued within 139 days and 90% within 189 days, covering January 2021 through September 15, 2026.

Typical wait48 daysmedian issued permit
Usually within139 days75% of records
Long-wait edge189 days90% of records
Evidence34issued permits

Not enough records for a year-over-year comparison.

New Construction permits in Forest Glen: wait distribution

For New Construction permits in Forest Glen, 34 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
8.8%
1–7 days
0.0%
8–30 days
23.5%
31–90 days
35.3%
91+ days
32.4%

Change over time

New Construction permits in Forest Glen: annual permit timing

New Construction permits in Forest Glen has 0 publishable issue-year cohorts spanning no qualifying years, representing 0 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction permits in Forest Glen: New Construction timing in comparable community areas

New Construction permits in Forest Glen has 34 issued records, a 48 days median, and a 139 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Belmont Cragin48 days110 days42
Forest Glen48 days139 days34
Washington Park48 days102 days108
Mckinley Park50 days148 days50
Jefferson Park46 days71 days78
Norwood Park50 days104 days62
Dunning51 days150 days39
Edgewater51 days112 days91