New Construction permits in Garfield Ridge
The typical new construction permit issued in Garfield Ridge took 57 days. The 75th-percentile wait was 182 days.
Records checked392021–Sep. 15, 2026
The short answer
Typical wait57 daysmedian issued permit
Usually within182 days75% of records
Long-wait edge372 days90% of records
Evidence39issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2025 | 13 | 51 days | 247 days | 267 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction timing in comparable community areas
| Report | Median | 75% within | Records |
|---|---|---|---|
| Garfield Ridge | 57 days | 182 days | 39 |
| Grand Boulevard | 57 days | 96 days | 245 |
| Humboldt Park | 55 days | 112 days | 227 |
| South Lawndale | 59 days | 187 days | 70 |
| Avondale | 54 days | 98 days | 107 |
| North Lawndale | 54 days | 145 days | 242 |
| Bridgeport | 53 days | 151 days | 125 |
| Mount Greenwood | 53 days | 105 days | 29 |