New Construction permits in South Lawndale

The typical new construction permit issued in South Lawndale took 59 days. The 75th-percentile wait was 187 days.

Records checked702021–Sep. 15, 2026

The short answer

Typical wait59 daysmedian issued permit
Usually within187 days75% of records
Long-wait edge254 days90% of records
Evidence70issued permits

Not enough records for a year-over-year comparison.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
12.9%
1–7 days
17.1%
8–30 days
8.6%
31–90 days
17.1%
91+ days
44.3%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021111 day98 days176 days
20231682 days184 days275 days
202415151 days244 days268 days
2026*114 days30 days51 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
South Lawndale59 days187 days70
Garfield Ridge57 days182 days39
Grand Boulevard57 days96 days245
West Ridge62 days125 days95
Humboldt Park55 days112 days227
Austin64 days137 days161
Avondale54 days98 days107
North Lawndale54 days145 days242