Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Austin

The typical new construction permit issued in Austin took 64 days. The 75th-percentile wait was 137 days.

Records checked1612021–Sep. 15, 2026

The short answer

Typical wait64 daysmedian issued permit
Usually within137 days75% of records
Long-wait edge245 days90% of records
Evidence161issued permits

The median was 26 days slower than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
15.5%
1–7 days
0.6%
8–30 days
18.0%
31–90 days
31.7%
91+ days
34.2%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20212420 days41 days100 days
20223421 days98 days155 days
20232878 days164 days288 days
202423149 days245 days272 days
20253258 days83 days141 days
2026*2091 days185 days288 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable community areas

ReportMedian75% withinRecords
Austin64 days137 days161
West Ridge62 days125 days95
South Lawndale59 days187 days70
Garfield Ridge57 days182 days39
Grand Boulevard57 days96 days245
Humboldt Park55 days112 days227
Pullman73 days128 days25
Avondale54 days98 days107