Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

New Construction permits in Pullman

The typical new construction permit issued in Pullman took 73 days. The 75th-percentile wait was 128 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked252021–Sep. 15, 2026

The short answer

For New Construction permits in Pullman, 25 issued permit records show a median processing time of 73 days; 75% were issued within 128 days and 90% within 233 days, covering January 2021 through September 15, 2026.

Typical wait73 daysmedian issued permit
Usually within128 days75% of records
Long-wait edge233 days90% of records
Evidence25issued permits

Not enough records for a year-over-year comparison.

New Construction permits in Pullman: wait distribution

For New Construction permits in Pullman, 25 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
8.0%
1–7 days
8.0%
8–30 days
8.0%
31–90 days
32.0%
91+ days
44.0%

Change over time

New Construction permits in Pullman: annual permit timing

New Construction permits in Pullman has 0 publishable issue-year cohorts spanning no qualifying years, representing 0 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction permits in Pullman: New Construction timing in comparable community areas

New Construction permits in Pullman has 25 issued records, a 73 days median, and a 128 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
Pullman73 days128 days25
Austin64 days137 days161
Portage Park82 days162 days76
West Ridge62 days125 days95
South Lawndale59 days187 days70
Garfield Ridge57 days182 days39
Grand Boulevard57 days96 days245
Humboldt Park55 days112 days227