Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Official community area

Humboldt Park permit processing times

For 3,185 issued permits in Humboldt Park, the median processing time was 1 day; 75% were issued within 24 days.

Records checked3,1852021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within24 days75% of records
Long-wait edge93 days90% of records
Evidence3,185issued permits

The median was 2 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
44.8%
1–7 days
18.7%
8–30 days
14.0%
31–90 days
12.2%
91+ days
10.2%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
20216450 days7 days59 days
20226190 days10 days76 days
20235760 days9 days71 days
20244656 days34 days118 days
202551712 days45 days110 days
2026*3638 days59 days132 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Nearby points in the citywide timing distribution

ReportMedian75% withinRecords
Albany Park1 day14 days2,213
Archer Heights1 day14 days812
Ashburn1 day10 days2,411
Auburn Gresham1 day11 days3,290
Austin1 day14 days5,647
Belmont Cragin1 day13 days2,724
Beverly1 day13 days1,644
Burnside1 day9.5 days227