Independent analysis of City of Chicago recordsData through Sep. 15, 2026

Community area × permit type

Express Permit Program permits in Mount Greenwood

The typical express permit program permit issued in Mount Greenwood took 1 day. The 75th-percentile wait was 6.8 days.

Records checked3942021–Sep. 15, 2026

The short answer

Typical wait1 daymedian issued permit
Usually within6.8 days75% of records
Long-wait edge21 days90% of records
Evidence394issued permits

The median was unchanged from the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
45.9%
1–7 days
32.5%
8–30 days
15.2%
31–90 days
3.3%
91+ days
3.0%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021440 days1 day7.4 days
2022350 days5.5 days22 days
2023412 days7 days601 days
20241071 day8 days20 days
2025951 day5 days21 days
2026*721 day6.2 days13 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program timing in comparable community areas

ReportMedian75% withinRecords
Albany Park1 day6 days997
Auburn Gresham1 day7 days1,679
Austin1 day7 days2,565
Avondale1 day6 days866
Beverly1 day7 days843
Brighton Park1 day9 days684
Burnside1 day5 days127
Chatham1 day7 days1,207