Renovation & Alteration permits in ZIP 60631
The median renovation & alteration permit wait in ZIP 60631 was 27 days, based on 481 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Renovation & Alteration permits in ZIP 60631, 481 issued permit records show a median processing time of 27 days; 75% were issued within 80 days and 90% within 163 days, covering January 2021 through September 15, 2026.
The median was 18 days slower than the previous 12 months.
Renovation & Alteration permits in ZIP 60631: wait distribution
For Renovation & Alteration permits in ZIP 60631, 481 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Renovation & Alteration permits in ZIP 60631: annual permit timing
Renovation & Alteration permits in ZIP 60631 has 6 publishable issue-year cohorts spanning 2021–2026, representing 481 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 103 | 6 days | 50 days | 115 days |
| 2022 | 99 | 0 days | 68 days | 134 days |
| 2023 | 87 | 37 days | 106 days | 185 days |
| 2024 | 61 | 46 days | 99 days | 208 days |
| 2025 | 78 | 40 days | 100 days | 177 days |
| 2026* | 53 | 47 days | 104 days | 204 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Renovation & Alteration permits in ZIP 60631: Renovation & Alteration timing in comparable ZIP codes
Renovation & Alteration permits in ZIP 60631 has 481 issued records, a 27 days median, and a 80 days 75th-percentile wait in this release.
More Renovation & Alteration permits in ZIP 60631 comparisons
The Renovation & Alteration permits in ZIP 60631 cohort contains 481 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60631 permits ZIP reportRenovation & Alteration citywide Type report