ZIP code × permit type
Express Permit Program permits in ZIP 60610
The median express permit program permit wait in ZIP 60610 was 4 days, based on 1,544 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Express Permit Program permits in ZIP 60610, 1,544 issued permit records show a median processing time of 4 days; 75% were issued within 17 days and 90% within 38 days, covering January 2021 through September 15, 2026.
The median was 5 days slower than the previous 12 months.
Express Permit Program permits in ZIP 60610: wait distribution
For Express Permit Program permits in ZIP 60610, 1,544 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Express Permit Program permits in ZIP 60610: annual permit timing
Express Permit Program permits in ZIP 60610 has 6 publishable issue-year cohorts spanning 2021–2026, representing 1,544 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 158 | 0 days | 5 days | 40 days |
| 2022 | 194 | 0 days | 7 days | 48 days |
| 2023 | 179 | 1 day | 11 days | 41 days |
| 2024 | 335 | 6 days | 14 days | 33 days |
| 2025 | 401 | 7 days | 20 days | 31 days |
| 2026* | 277 | 7 days | 20 days | 46 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Express Permit Program permits in ZIP 60610: Express Permit Program timing in comparable ZIP codes
Express Permit Program permits in ZIP 60610 has 1,544 issued records, a 4 days median, and a 17 days 75th-percentile wait in this release.
More Express Permit Program permits in ZIP 60610 comparisons
The Express Permit Program permits in ZIP 60610 cohort contains 1,544 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60610 permits ZIP reportExpress Permit Program citywide Type report