Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Express Permit Program permits in ZIP 60601

The median express permit program permit wait in ZIP 60601 was 3 days, based on 2,039 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked2,0392021–Sep. 15, 2026

The short answer

For Express Permit Program permits in ZIP 60601, 2,039 issued permit records show a median processing time of 3 days; 75% were issued within 14 days and 90% within 38 days, covering January 2021 through September 15, 2026.

Typical wait3 daysmedian issued permit
Usually within14 days75% of records
Long-wait edge38 days90% of records
Evidence2,039issued permits

The median was unchanged from the previous 12 months.

Express Permit Program permits in ZIP 60601: wait distribution

For Express Permit Program permits in ZIP 60601, 2,039 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
36.3%
1–7 days
30.8%
8–30 days
19.7%
31–90 days
10.0%
91+ days
3.2%

Change over time

Express Permit Program permits in ZIP 60601: annual permit timing

Express Permit Program permits in ZIP 60601 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,039 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20213340 days8 days28 days
20223421 day26 days46 days
20233167 days29 days104 days
20244686 days16 days34 days
20253643 days8 days18 days
2026*2153 days6 days15 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Express Permit Program permits in ZIP 60601: Express Permit Program timing in comparable ZIP codes

Express Permit Program permits in ZIP 60601 has 2,039 issued records, a 3 days median, and a 14 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 606013 days14 days2,039
ZIP 606113 days11 days4,260
ZIP 606223 days12 days1,582
ZIP 606533 days12 days773
ZIP 606044 days15 days677
ZIP 606062 days20 days4,573
ZIP 606072 days14 days1,882
ZIP 606104 days17 days1,544