ZIP boundary report
Permit processing times in ZIP 60601
Across 3,363 issued permits assigned to ZIP 60601, the median processing time was 3 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60601, 3,363 issued permit records show a median processing time of 3 days; 75% were issued within 15 days and 90% within 48 days, covering January 2021 through September 15, 2026.
The median was unchanged from the previous 12 months.
Permit processing times in ZIP 60601: wait distribution
For Permit processing times in ZIP 60601, 3,363 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60601: annual permit timing
Permit processing times in ZIP 60601 has 6 publishable issue-year cohorts spanning 2021–2026, representing 3,363 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 614 | 0 days | 14 days | 46 days |
| 2022 | 611 | 0 days | 12 days | 42 days |
| 2023 | 530 | 2 days | 22 days | 70 days |
| 2024 | 664 | 6 days | 20 days | 49 days |
| 2025 | 570 | 5 days | 14 days | 38 days |
| 2026* | 374 | 4 days | 13 days | 49 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60601: ZIP codes with similar overall timing
Permit processing times in ZIP 60601 has 3,363 issued records, a 3 days median, and a 15 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60601 comparisons
The Permit processing times in ZIP 60601 cohort contains 3,363 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 3 daysRenovation & Alteration 6.5 daysElevator Equipment 0 daysEasy Permit Process 1 daySigns 43 daysScaffolding 0 days