ZIP boundary report
Permit processing times in ZIP 60606
Across 6,775 issued permits assigned to ZIP 60606, the median processing time was 2 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60606, 6,775 issued permit records show a median processing time of 2 days; 75% were issued within 15 days and 90% within 38 days, covering January 2021 through September 15, 2026.
The median was unchanged from the previous 12 months.
Permit processing times in ZIP 60606: wait distribution
For Permit processing times in ZIP 60606, 6,775 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60606: annual permit timing
Permit processing times in ZIP 60606 has 6 publishable issue-year cohorts spanning 2021–2026, representing 6,775 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 1,208 | 0 days | 14 days | 35 days |
| 2022 | 1,175 | 0 days | 17 days | 42 days |
| 2023 | 1,349 | 3 days | 28 days | 87 days |
| 2024 | 1,144 | 5 days | 21 days | 36 days |
| 2025 | 1,118 | 3 days | 7.8 days | 19 days |
| 2026* | 781 | 3 days | 7 days | 22 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60606: ZIP codes with similar overall timing
Permit processing times in ZIP 60606 has 6,775 issued records, a 2 days median, and a 15 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60606 comparisons
The Permit processing times in ZIP 60606 cohort contains 6,775 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 2 daysRenovation & Alteration 2 daysEasy Permit Process 0 daysElevator Equipment 0 daysSigns 22 daysScaffolding 0 daysNew Construction 1 day