ZIP boundary report
Permit processing times in ZIP 60621
Across 2,516 issued permits assigned to ZIP 60621, the median processing time was 2 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60621, 2,516 issued permit records show a median processing time of 2 days; 75% were issued within 23 days and 90% within 98 days, covering January 2021 through September 15, 2026.
The median was unchanged from the previous 12 months.
Permit processing times in ZIP 60621: wait distribution
For Permit processing times in ZIP 60621, 2,516 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60621: annual permit timing
Permit processing times in ZIP 60621 has 6 publishable issue-year cohorts spanning 2021–2026, representing 2,516 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 522 | 0 days | 9 days | 74 days |
| 2022 | 473 | 0 days | 7 days | 57 days |
| 2023 | 438 | 0 days | 13 days | 95 days |
| 2024 | 419 | 8 days | 38 days | 113 days |
| 2025 | 394 | 8 days | 37 days | 113 days |
| 2026* | 270 | 9 days | 56 days | 126 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60621: ZIP codes with similar overall timing
Permit processing times in ZIP 60621 has 2,516 issued records, a 2 days median, and a 23 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60621 comparisons
The Permit processing times in ZIP 60621 cohort contains 2,516 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 35 daysEasy Permit Process 0 daysWrecking & Demolition 0 daysSigns 16 daysElevator Equipment 0 daysReinstated Permit 0 daysNew Construction 42 days