ZIP boundary report
Permit processing times in ZIP 60618
Across 6,576 issued permits assigned to ZIP 60618, the median processing time was 2 days.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Permit processing times in ZIP 60618, 6,576 issued permit records show a median processing time of 2 days; 75% were issued within 27 days and 90% within 87 days, covering January 2021 through September 15, 2026.
The median was 1.5 days slower than the previous 12 months.
Permit processing times in ZIP 60618: wait distribution
For Permit processing times in ZIP 60618, 6,576 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Permit processing times in ZIP 60618: annual permit timing
Permit processing times in ZIP 60618 has 6 publishable issue-year cohorts spanning 2021–2026, representing 6,576 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 1,403 | 0 days | 10 days | 70 days |
| 2022 | 1,300 | 0 days | 6 days | 69 days |
| 2023 | 1,118 | 0 days | 15 days | 95 days |
| 2024 | 1,108 | 8.5 days | 35 days | 87 days |
| 2025 | 974 | 9 days | 42 days | 108 days |
| 2026* | 673 | 11 days | 46 days | 108 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Permit processing times in ZIP 60618: ZIP codes with similar overall timing
Permit processing times in ZIP 60618 has 6,576 issued records, a 2 days median, and a 27 days 75th-percentile wait in this release.
More Permit processing times in ZIP 60618 comparisons
The Permit processing times in ZIP 60618 cohort contains 6,576 issued records; related links retain separate location and permit-category cohorts.
Express Permit Program 1 dayRenovation & Alteration 31 daysEasy Permit Process 0 daysSigns 20 daysNew Construction 45 daysWrecking & Demolition 0 daysElevator Equipment 0 daysReinstated Permit 0 days