Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

Signs permits in ZIP 60618

The median signs permit wait in ZIP 60618 was 20 days, based on 601 issued records.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked6012021–Sep. 15, 2026

The short answer

For Signs permits in ZIP 60618, 601 issued permit records show a median processing time of 20 days; 75% were issued within 51 days and 90% within 134 days, covering January 2021 through September 15, 2026.

Typical wait20 daysmedian issued permit
Usually within51 days75% of records
Long-wait edge134 days90% of records
Evidence601issued permits

The median was 8 days slower than the previous 12 months.

Signs permits in ZIP 60618: wait distribution

For Signs permits in ZIP 60618, 601 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
1.5%
1–7 days
30.3%
8–30 days
29.1%
31–90 days
21.8%
91+ days
17.3%

Change over time

Signs permits in ZIP 60618: annual permit timing

Signs permits in ZIP 60618 has 6 publishable issue-year cohorts spanning 2021–2026, representing 601 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20211069 days74 days157 days
20221265 days21 days112 days
202310812 days98 days134 days
202412128 days48 days118 days
20258230 days44 days81 days
2026*5837 days62 days149 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Signs permits in ZIP 60618: Signs timing in comparable ZIP codes

Signs permits in ZIP 60618 has 601 issued records, a 20 days median, and a 51 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
ZIP 6060920 days79 days217
ZIP 6061820 days51 days601
ZIP 6064120 days44 days384
ZIP 6065220 days71 days177
ZIP 6066020 days56 days102
ZIP 6062821 days71 days115
ZIP 6063421 days38 days131
ZIP 6065521 days42 days83