Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP code × permit type

New Construction permits in ZIP 60618

The median new construction permit wait in ZIP 60618 was 45 days, based on 503 issued records.

Records checked5032021–Sep. 15, 2026

The short answer

Typical wait45 daysmedian issued permit
Usually within86 days75% of records
Long-wait edge178 days90% of records
Evidence503issued permits

The median was 14 days faster than the previous 12 months.

How the waits are distributed

Median is only the middle. This shows how often issued permits fell into each elapsed-time band.

Same day
24.3%
1–7 days
4.4%
8–30 days
11.9%
31–90 days
35.4%
91+ days
24.1%

Change over time

Annual permit timing

Issue yearRecordsMedian75th percentile90th percentile
2021990 days64 days96 days
2022901.5 days66 days140 days
20237347 days79 days220 days
20249461 days98 days180 days
20259274 days136 days241 days
2026*5556 days82 days130 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

New Construction timing in comparable ZIP codes

ReportMedian75% withinRecords
ZIP 6061845 days86 days503
ZIP 6062345 days146 days253
ZIP 6061944 days108 days43
ZIP 6062142 days137 days36
ZIP 6061648 days128 days190
ZIP 6064648 days146 days42
ZIP 6064742 days105 days322
ZIP 6062941 days116 days45