ZIP code × permit type
New Construction permits in ZIP 60618
The median new construction permit wait in ZIP 60618 was 45 days, based on 503 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60618, 503 issued permit records show a median processing time of 45 days; 75% were issued within 86 days and 90% within 178 days, covering January 2021 through September 15, 2026.
The median was 14 days faster than the previous 12 months.
New Construction permits in ZIP 60618: wait distribution
For New Construction permits in ZIP 60618, 503 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60618: annual permit timing
New Construction permits in ZIP 60618 has 6 publishable issue-year cohorts spanning 2021–2026, representing 503 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 99 | 0 days | 64 days | 96 days |
| 2022 | 90 | 1.5 days | 66 days | 140 days |
| 2023 | 73 | 47 days | 79 days | 220 days |
| 2024 | 94 | 61 days | 98 days | 180 days |
| 2025 | 92 | 74 days | 136 days | 241 days |
| 2026* | 55 | 56 days | 82 days | 130 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60618: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60618 has 503 issued records, a 45 days median, and a 86 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60618 comparisons
The New Construction permits in ZIP 60618 cohort contains 503 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60618 permits ZIP reportNew Construction citywide Type report