ZIP code × permit type
New Construction permits in ZIP 60647
The median new construction permit wait in ZIP 60647 was 42 days, based on 322 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60647, 322 issued permit records show a median processing time of 42 days; 75% were issued within 105 days and 90% within 226 days, covering January 2021 through September 15, 2026.
The median was 8.5 days faster than the previous 12 months.
New Construction permits in ZIP 60647: wait distribution
For New Construction permits in ZIP 60647, 322 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60647: annual permit timing
New Construction permits in ZIP 60647 has 6 publishable issue-year cohorts spanning 2021–2026, representing 322 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 72 | 3 days | 75 days | 177 days |
| 2022 | 61 | 0 days | 54 days | 133 days |
| 2023 | 43 | 25 days | 101 days | 212 days |
| 2024 | 49 | 62 days | 151 days | 220 days |
| 2025 | 52 | 55 days | 103 days | 251 days |
| 2026* | 45 | 68 days | 157 days | 362 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60647: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60647 has 322 issued records, a 42 days median, and a 105 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60647 comparisons
The New Construction permits in ZIP 60647 cohort contains 322 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60647 permits ZIP reportNew Construction citywide Type report