ZIP code × permit type
New Construction permits in ZIP 60616
The median new construction permit wait in ZIP 60616 was 48 days, based on 190 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60616, 190 issued permit records show a median processing time of 48 days; 75% were issued within 128 days and 90% within 287 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60616: wait distribution
For New Construction permits in ZIP 60616, 190 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60616: annual permit timing
New Construction permits in ZIP 60616 has 6 publishable issue-year cohorts spanning 2021–2026, representing 190 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 46 | 33 days | 93 days | 170 days |
| 2022 | 32 | 0 days | 56 days | 100 days |
| 2023 | 23 | 40 days | 237 days | 422 days |
| 2024 | 26 | 74 days | 224 days | 316 days |
| 2025 | 30 | 70 days | 126 days | 177 days |
| 2026* | 33 | 91 days | 209 days | 340 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60616: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60616 has 190 issued records, a 48 days median, and a 128 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60616 comparisons
The New Construction permits in ZIP 60616 cohort contains 190 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60616 permits ZIP reportNew Construction citywide Type report