New Construction permits in ZIP 60632
The median new construction permit wait in ZIP 60632 was 52 days, based on 122 issued records.
Records checked1222021–Sep. 15, 2026
The short answer
Typical wait52 daysmedian issued permit
Usually within120 days75% of records
Long-wait edge351 days90% of records
Evidence122issued permits
Not enough records for a year-over-year comparison.
How the waits are distributed
Median is only the middle. This shows how often issued permits fell into each elapsed-time band.
Change over time
Annual permit timing
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 24 | 18 days | 53 days | 71 days |
| 2022 | 30 | 24 days | 121 days | 207 days |
| 2023 | 18 | 54 days | 109 days | 209 days |
| 2024 | 19 | 216 days | 387 days | 550 days |
| 2025 | 16 | 72 days | 288 days | 383 days |
| 2026* | 15 | 67 days | 94 days | 101 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.