New Construction permits in ZIP 60632
The median new construction permit wait in ZIP 60632 was 52 days, based on 122 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For New Construction permits in ZIP 60632, 122 issued permit records show a median processing time of 52 days; 75% were issued within 120 days and 90% within 351 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
New Construction permits in ZIP 60632: wait distribution
For New Construction permits in ZIP 60632, 122 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
New Construction permits in ZIP 60632: annual permit timing
New Construction permits in ZIP 60632 has 6 publishable issue-year cohorts spanning 2021–2026, representing 122 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 24 | 18 days | 53 days | 71 days |
| 2022 | 30 | 24 days | 121 days | 207 days |
| 2023 | 18 | 54 days | 109 days | 209 days |
| 2024 | 19 | 216 days | 387 days | 550 days |
| 2025 | 16 | 72 days | 288 days | 383 days |
| 2026* | 15 | 67 days | 94 days | 101 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
New Construction permits in ZIP 60632: New Construction timing in comparable ZIP codes
New Construction permits in ZIP 60632 has 122 issued records, a 52 days median, and a 120 days 75th-percentile wait in this release.
More New Construction permits in ZIP 60632 comparisons
The New Construction permits in ZIP 60632 cohort contains 122 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60632 permits ZIP reportNew Construction citywide Type report