Independent analysis of City of Chicago recordsData through Sep. 15, 2026

ZIP boundary report

Permit processing times in ZIP 60632

Across 3,446 issued permits assigned to ZIP 60632, the median processing time was 2 days.

Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026

Records checked3,4462021–Sep. 15, 2026

The short answer

For Permit processing times in ZIP 60632, 3,446 issued permit records show a median processing time of 2 days; 75% were issued within 15 days and 90% within 75 days, covering January 2021 through September 15, 2026.

Typical wait2 daysmedian issued permit
Usually within15 days75% of records
Long-wait edge75 days90% of records
Evidence3,446issued permits

The median was 4 days faster than the previous 12 months.

Permit processing times in ZIP 60632: wait distribution

For Permit processing times in ZIP 60632, 3,446 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.

Same day
42.1%
1–7 days
20.9%
8–30 days
18.7%
31–90 days
9.8%
91+ days
8.5%

Change over time

Permit processing times in ZIP 60632: annual permit timing

Permit processing times in ZIP 60632 has 6 publishable issue-year cohorts spanning 2021–2026, representing 3,446 issued records in the annual table.

Issue yearRecordsMedian75th percentile90th percentile
20217610 days8 days42 days
20226530 days11 days54 days
20235450 days13 days90 days
20246114 days19 days78 days
202549710 days30 days101 days
2026*3796 days31 days91 days

*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.

Context

Permit processing times in ZIP 60632: ZIP codes with similar overall timing

Permit processing times in ZIP 60632 has 3,446 issued records, a 2 days median, and a 15 days 75th-percentile wait in this release.

ReportMedian75% withinRecords
606062 days15 days6,775
606082 days26 days4,677
606132 days21 days2,994
606162 days25 days2,939
606182 days27 days6,576
606212 days23 days2,516
606232 days24 days4,182
606242 days21 days2,944