Elevator Equipment permits in ZIP 60632
The median elevator equipment permit wait in ZIP 60632 was 0 days, based on 54 issued records.
Source: City of Chicago Building Permits · Issued-permit cohort · Updated Sep. 16, 2026
The short answer
For Elevator Equipment permits in ZIP 60632, 54 issued permit records show a median processing time of 0 days; 75% were issued within 0 days and 90% within 0 days, covering January 2021 through September 15, 2026.
Not enough records for a year-over-year comparison.
Elevator Equipment permits in ZIP 60632: wait distribution
For Elevator Equipment permits in ZIP 60632, 54 issued permits are distributed across five elapsed-time bands from same-day issuance through waits of 91 days or longer.
Change over time
Elevator Equipment permits in ZIP 60632: annual permit timing
Elevator Equipment permits in ZIP 60632 has 3 publishable issue-year cohorts spanning 2021–2023, representing 35 issued records in the annual table.
| Issue year | Records | Median | 75th percentile | 90th percentile |
|---|---|---|---|---|
| 2021 | 13 | 0 days | 0 days | 0 days |
| 2022 | 12 | 0 days | 0 days | 0 days |
| 2023 | 10 | 0 days | 0 days | 2.3 days |
*2026 is partial through Sep. 15. Year labels use the permit issue date, not the application date.
Context
Elevator Equipment permits in ZIP 60632: Elevator Equipment timing in comparable ZIP codes
Elevator Equipment permits in ZIP 60632 has 54 issued records, a 0 days median, and a 0 days 75th-percentile wait in this release.
More Elevator Equipment permits in ZIP 60632 comparisons
The Elevator Equipment permits in ZIP 60632 cohort contains 54 issued records; related links retain separate location and permit-category cohorts.
All ZIP 60632 permits ZIP reportElevator Equipment citywide Type report